How long does a Commercial / Multi Family Project permit take in Deer Run, Calgary?

Rolling 24 months · Sample: 8
Median days · Applied → Issued
93 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
279 days
From permit issuance to completion
City-wide median
42 days
Deer Run is 51 days slower

Recent examples in Deer Run

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15062Improvement2026-08-102026-09-1132$770K
BP2026-03989NewGraham Construction and Engineering2026-03-162026-08-11148$45.4M
BP2026-06831ImprovementCentra Projects Alberta2026-04-262026-05-2832$1M
BP2025-23939ImprovementGraham Construction and Engineering2025-12-182026-04-15118$10M
BP2025-16772Improvement2025-08-272026-01-08134$1.3M