How long does a Commercial / Multi Family Project permit take in Deer Run, Calgary?
Median days · Applied → Issued
93 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
279 days
From permit issuance to completion
City-wide median
42 days
Deer Run is 51 days slower
Recent examples in Deer Run
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15062 | Improvement | — | 2026-08-10 | 2026-09-11 | 32 | $770K |
| BP2026-03989 | New | Graham Construction and Engineering | 2026-03-16 | 2026-08-11 | 148 | $45.4M |
| BP2026-06831 | Improvement | Centra Projects Alberta | 2026-04-26 | 2026-05-28 | 32 | $1M |
| BP2025-23939 | Improvement | Graham Construction and Engineering | 2025-12-18 | 2026-04-15 | 118 | $10M |
| BP2025-16772 | Improvement | — | 2025-08-27 | 2026-01-08 | 134 | $1.3M |