How long does a Commercial / Multi Family Project permit take in Dalhousie, Calgary?
Median days · Applied → Issued
43 days
Sample: 15 permits, last 24 months
Median days · Issued → Completed
89 days
From permit issuance to completion
City-wide median
42 days
Dalhousie is 1 days slower
Recent examples in Dalhousie
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2025-20676 | New | Ashmore Homes | 2025-10-22 | 2026-08-14 | 296 | $1.1M |
| BP2026-06403 | Improvement | — | 2026-04-20 | 2026-07-15 | 86 | $800K |
| BP2026-05220 | Improvement | Tayo Construction | 2026-04-03 | 2026-04-21 | 18 | $230K |
| BP2026-04042 | Improvement | Esa Construction | 2026-03-17 | 2026-03-19 | 2 | $97K |
| BP2025-16771 | Improvement | — | 2025-08-27 | 2025-12-08 | 103 | $100 |