How long does a Residential Improvement Project permit take in Crestmont, Calgary?

Rolling 24 months · Sample: 53
Median days · Applied → Issued
14 days
Sample: 53 permits, last 24 months
Median days · Issued → Completed
36 days
From permit issuance to completion
City-wide median
17 days
Crestmont is 3 days faster

Recent examples in Crestmont

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-12792Improvement2026-07-092026-09-0861$39K
BP2026-16202ImprovementAbove Grade Basements2026-08-252026-09-0814$47K
BP2026-15261ImprovementUmbrella Construction2026-08-122026-08-2614$32K
BP2026-13916Improvement2026-07-242026-08-1118$63K
BP2026-14536NewQatest Home Builder2026-08-012026-08-010$0

Other permit types in Crestmont