How long does a Residential Improvement Project permit take in Crestmont, Calgary?
Median days · Applied → Issued
14 days
Sample: 53 permits, last 24 months
Median days · Issued → Completed
36 days
From permit issuance to completion
City-wide median
17 days
Crestmont is 3 days faster
Recent examples in Crestmont
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12792 | Improvement | — | 2026-07-09 | 2026-09-08 | 61 | $39K |
| BP2026-16202 | Improvement | Above Grade Basements | 2026-08-25 | 2026-09-08 | 14 | $47K |
| BP2026-15261 | Improvement | Umbrella Construction | 2026-08-12 | 2026-08-26 | 14 | $32K |
| BP2026-13916 | Improvement | — | 2026-07-24 | 2026-08-11 | 18 | $63K |
| BP2026-14536 | New | Qatest Home Builder | 2026-08-01 | 2026-08-01 | 0 | $0 |