How long does a Commercial / Multi Family Project permit take in Cranston, Calgary?
Median days · Applied → Issued
41 days
Sample: 9 permits, last 24 months
Median days · Issued → Completed
44 days
From permit issuance to completion
City-wide median
42 days
Cranston is 1 days faster
Recent examples in Cranston
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-01616 | Improvement | — | 2026-02-03 | 2026-04-20 | 76 | $0 |
| BP2026-01639 | Improvement | — | 2026-02-03 | 2026-02-23 | 20 | $50K |
| BP2025-17093 | Improvement | — | 2025-09-03 | 2026-01-21 | 140 | $2K |
| BP2025-16796 | Improvement | — | 2025-08-28 | 2025-10-08 | 41 | $550K |
| BP2025-14592 | Improvement | — | 2025-07-28 | 2025-08-20 | 23 | $133K |