How long does a Residential Improvement Project permit take in Country Hills, Calgary?
Median days · Applied → Issued
17 days
Sample: 63 permits, last 24 months
Median days · Issued → Completed
77 days
From permit issuance to completion
City-wide median
17 days
Same as Country Hills
Recent examples in Country Hills
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-16508 | New | — | 2026-08-28 | 2026-09-11 | 14 | $42K |
| BP2026-13888 | New | Abby Renovations | 2026-07-23 | 2026-08-25 | 33 | $51K |
| BP2026-12198 | Improvement | — | 2026-06-30 | 2026-08-11 | 42 | $42K |
| BP2026-12355 | Improvement | True North Concrete Cutting and Coring | 2026-07-03 | 2026-08-06 | 34 | $15K |
| BP2026-12705 | New | — | 2026-07-08 | 2026-08-04 | 27 | $12K |