How long does a Residential Improvement Project permit take in Country Hills Village, Calgary?
Median days · Applied → Issued
14 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
25 days
From permit issuance to completion
City-wide median
17 days
Country Hills Village is 3 days faster
Recent examples in Country Hills Village
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15265 | Improvement | Reimagine Builders | 2026-08-12 | 2026-08-26 | 14 | $14K |
| BP2026-11273 | Improvement | — | 2026-06-18 | 2026-07-06 | 18 | $22K |
| BP2025-12048 | Improvement | A1 Calgary Construction | 2025-06-23 | 2025-07-06 | 13 | $27K |
| BP2025-03027 | Improvement | — | 2025-02-21 | 2025-03-05 | 12 | $23K |
| BP2025-01384 | Improvement | — | 2025-01-25 | 2025-02-04 | 10 | $22K |