How long does a Commercial / Multi Family Project permit take in Copperfield, Calgary?
Median days · Applied → Issued
38 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
139 days
From permit issuance to completion
City-wide median
42 days
Copperfield is 4 days faster
Recent examples in Copperfield
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06922 | Improvement | — | 2026-04-27 | 2026-06-17 | 51 | $500 |
| BP2026-07584 | Improvement | On Side Restoration | 2026-05-05 | 2026-05-27 | 22 | $25K |
| BP2025-15588 | New | Eagle Crest Construction | 2025-08-11 | 2026-02-18 | 191 | $1.1M |
| BP2025-22707 | Improvement | — | 2025-11-25 | 2025-12-30 | 35 | $40K |
| BP2025-06415 | Improvement | Yyc Homes | 2025-04-11 | 2025-07-10 | 90 | $15K |