How long does a Commercial / Multi Family Project permit take in Cliff Bungalow, Calgary?
Median days · Applied → Issued
36 days
Sample: 31 permits, last 24 months
Median days · Issued → Completed
101 days
From permit issuance to completion
City-wide median
42 days
Cliff Bungalow is 6 days faster
Recent examples in Cliff Bungalow
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-13535 | Improvement | — | 2026-07-20 | 2026-07-24 | 4 | $34K |
| BP2026-11659 | Improvement | — | 2026-06-24 | 2026-07-21 | 27 | $0 |
| BP2026-11484 | Improvement | — | 2026-06-22 | 2026-07-15 | 23 | $20K |
| BP2026-10083 | Improvement | Chinook Elevator | 2026-06-04 | 2026-06-29 | 25 | $325K |
| BP2026-05386 | Improvement | — | 2026-04-07 | 2026-05-26 | 49 | $50K |