Median days · Applied → Issued
27 days
Sample: 256 permits, last 24 months
Median days · Issued → Completed
103 days
From permit issuance to completion
City-wide median
17 days
Cityscape is 10 days slower
Recent examples in Cityscape
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-05405 | Improvement | — | 2026-04-07 | 2026-09-09 | 155 | $59K |
| BP2026-16119 | Improvement | — | 2026-08-24 | 2026-09-08 | 15 | $31K |
| BP2026-15426 | Improvement | A2z Reno Constructions | 2026-08-14 | 2026-09-02 | 19 | $60K |
| BP2026-11972 | Improvement | Reliable Projects | 2026-06-28 | 2026-08-31 | 64 | $70K |
| BP2026-11956 | Improvement | Reliable Projects | 2026-06-27 | 2026-08-26 | 60 | $70K |