How long does a Residential Improvement Project permit take in Christie Park, Calgary?
Median days · Applied → Issued
15 days
Sample: 27 permits, last 24 months
Median days · Issued → Completed
110 days
From permit issuance to completion
City-wide median
17 days
Christie Park is 2 days faster
Recent examples in Christie Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14897 | Improvement | — | 2026-08-07 | 2026-09-01 | 25 | $20K |
| BP2026-14464 | Improvement | S I S Supply Install Services | 2026-07-31 | 2026-08-12 | 12 | $3K |
| BP2026-12117 | Improvement | — | 2026-06-30 | 2026-07-13 | 13 | $46K |
| BP2026-07806 | Improvement | — | 2026-05-07 | 2026-06-26 | 50 | $47K |
| BP2026-09305 | Improvement | True North Concrete Cutting and Coring | 2026-05-27 | 2026-06-08 | 12 | $4K |