How long does a Commercial / Multi Family Project permit take in Chinatown, Calgary?
Median days · Applied → Issued
30 days
Sample: 49 permits, last 24 months
Median days · Issued → Completed
109 days
From permit issuance to completion
City-wide median
42 days
Chinatown is 12 days faster
Recent examples in Chinatown
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15931 | Improvement | — | 2026-08-21 | 2026-09-08 | 18 | $8K |
| BP2026-15186 | Improvement | — | 2026-08-11 | 2026-09-02 | 22 | $561K |
| BP2026-13115 | Improvement | — | 2026-07-14 | 2026-08-13 | 30 | $120K |
| BP2026-13503 | Improvement | Seagate Contract Management | 2026-07-20 | 2026-08-12 | 23 | $80K |
| BP2026-12136 | Unspecified | — | 2026-06-30 | 2026-07-30 | 30 | $922K |