How long does a Residential Improvement Project permit take in Cedarbrae, Calgary?
Median days · Applied → Issued
20 days
Sample: 59 permits, last 24 months
Median days · Issued → Completed
73 days
From permit issuance to completion
City-wide median
17 days
Cedarbrae is 3 days slower
Recent examples in Cedarbrae
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15825 | Improvement | Notorious Suites Royal Radon | 2026-08-20 | 2026-09-09 | 20 | $50K |
| BP2026-15545 | Improvement | — | 2026-08-17 | 2026-08-28 | 11 | $4K |
| BP2026-14034 | Improvement | My Home Handyman | 2026-07-27 | 2026-08-25 | 29 | $4K |
| BP2026-14486 | Improvement | Mika C | 2026-07-31 | 2026-08-25 | 25 | $60K |
| BP2026-14026 | Improvement | Mer Building Services | 2026-07-26 | 2026-08-17 | 22 | $22K |