How long does a Commercial / Multi Family Project permit take in Canada Olympic Park, Calgary?
Median days · Applied → Issued
37 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
92 days
From permit issuance to completion
City-wide median
42 days
Canada Olympic Park is 5 days faster
Recent examples in Canada Olympic Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-02769 | Unspecified | — | 2026-02-24 | 2026-02-27 | 3 | $500 |
| BP2025-08018 | Improvement | — | 2025-05-01 | 2025-05-23 | 22 | $120K |
| BP2025-05474 | Unspecified | — | 2025-03-31 | 2025-05-21 | 51 | $70K |
| BP2025-05777 | Improvement | — | 2025-04-03 | 2025-04-18 | 15 | $1K |
| BP2024-18343 | Improvement | EllisDon Construction | 2024-08-30 | 2024-12-11 | 103 | $987K |