How long does a Demolition permit take in Calgary International Airport, Calgary?
Median days · Applied → Issued
6 days
Sample: 3 permits, last 24 months
Median days · Issued → Completed
85 days
From permit issuance to completion
City-wide median
4 days
Calgary International Airport is 2 days slower
Recent examples in Calgary International Airport
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12806 | Demolition | Bird Construction Company | 2026-07-09 | 2026-07-17 | 8 | $0 |
| BP2025-09670 | Demolition | Qm Environmental | 2025-05-23 | 2025-05-29 | 6 | $0 |
| BP2025-09671 | Demolition | Qm Environmental | 2025-05-23 | 2025-05-29 | 6 | $0 |