How long does a Commercial / Multi Family Project permit take in Burns Industrial, Calgary?
Median days · Applied → Issued
41 days
Sample: 46 permits, last 24 months
Median days · Issued → Completed
86 days
From permit issuance to completion
City-wide median
42 days
Burns Industrial is 1 days faster
Recent examples in Burns Industrial
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14478 | Improvement | — | 2026-07-31 | 2026-09-10 | 41 | $250K |
| BP2026-15923 | Unspecified | — | 2026-08-21 | 2026-08-25 | 4 | $7K |
| BP2026-14252 | Improvement | — | 2026-07-28 | 2026-08-21 | 24 | $300K |
| BP2026-12679 | Improvement | — | 2026-07-08 | 2026-08-04 | 27 | $250K |
| BP2026-10753 | Improvement | — | 2026-06-12 | 2026-07-17 | 35 | $4K |