How long does a Single Construction Permit permit take in Britannia, Calgary?

Rolling 24 months · Sample: 7
Median days · Applied → Issued
62 days
Sample: 7 permits, last 24 months
Median days · Issued → Completed
488 days
From permit issuance to completion
City-wide median
18 days
Britannia is 44 days slower

Recent examples in Britannia

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-02812NewVesta Properties2026-02-252026-04-2256$0
BP2025-20497NewGallaghers Homes2025-10-202025-11-2132$770K
BP2025-09011NewRockwood Custom Homes2025-05-142025-10-03142$1.1M
BP2025-09132NewHndl Homes2025-05-152025-07-1662$0
BP2025-09370New2025-05-202025-05-222$668K