How long does a Commercial / Multi Family Project permit take in Bridlewood, Calgary?
Median days · Applied → Issued
36 days
Sample: 10 permits, last 24 months
Median days · Issued → Completed
314 days
From permit issuance to completion
City-wide median
42 days
Bridlewood is 6 days faster
Recent examples in Bridlewood
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-06057 | Unspecified | — | 2026-04-16 | 2026-04-21 | 5 | $4K |
| BP2025-19510 | Improvement | — | 2025-10-03 | 2025-11-18 | 46 | $1K |
| BP2025-16721 | Improvement | — | 2025-08-27 | 2025-10-06 | 40 | $7.5M |
| BP2025-05835 | Improvement | — | 2025-04-03 | 2025-07-02 | 90 | $35K |
| BP2024-25938 | Improvement | — | 2024-12-16 | 2025-04-10 | 115 | $400K |