How long does a Commercial / Multi Family Project permit take in Belmont, Calgary?

Rolling 24 months · Sample: 78
Median days · Applied → Issued
75 days
Sample: 78 permits, last 24 months
Median days · Issued → Completed
198 days
From permit issuance to completion
City-wide median
42 days
Belmont is 33 days slower

Recent examples in Belmont

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-14627Improvement2026-08-042026-08-3127$100K
BP2026-11794NewCity Vibe Developments2026-06-252026-08-2662$495K
BP2026-04664NewCity Vibe Developments2026-03-252026-08-10138$50.5M
BP2026-12162Improvement2026-06-302026-07-3131$800K
BP2026-02524NewHomes by Avi2026-02-192026-06-24125$950K