How long does a Commercial / Multi Family Project permit take in Belmont, Calgary?
Median days · Applied → Issued
75 days
Sample: 78 permits, last 24 months
Median days · Issued → Completed
198 days
From permit issuance to completion
City-wide median
42 days
Belmont is 33 days slower
Recent examples in Belmont
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14627 | Improvement | — | 2026-08-04 | 2026-08-31 | 27 | $100K |
| BP2026-11794 | New | City Vibe Developments | 2026-06-25 | 2026-08-26 | 62 | $495K |
| BP2026-04664 | New | City Vibe Developments | 2026-03-25 | 2026-08-10 | 138 | $50.5M |
| BP2026-12162 | Improvement | — | 2026-06-30 | 2026-07-31 | 31 | $800K |
| BP2026-02524 | New | Homes by Avi | 2026-02-19 | 2026-06-24 | 125 | $950K |