How long does a Residential Improvement Project permit take in Bel-Aire, Calgary?
Median days · Applied → Issued
18 days
Sample: 8 permits, last 24 months
Median days · Issued → Completed
247 days
From permit issuance to completion
City-wide median
17 days
Bel-Aire is 1 days slower
Recent examples in Bel-Aire
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-14343 | Improvement | — | 2026-07-29 | 2026-08-13 | 15 | $270K |
| BP2025-22930 | Improvement | Suncoast Enclosures | 2025-11-30 | 2026-01-06 | 37 | $103K |
| BP2025-11051 | New | Rockwood Custom Homes | 2025-06-10 | 2025-06-30 | 20 | $100K |
| BP2025-07250 | Improvement | Fresh Start Projects | 2025-04-23 | 2025-05-06 | 13 | $102K |
| BP2025-04861 | Improvement | Rock Creek Builders 2014 | 2025-03-21 | 2025-04-02 | 12 | $98K |