How long does a Commercial / Multi Family Project permit take in Bayview, Calgary?
Median days · Applied → Issued
31 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
106 days
From permit issuance to completion
City-wide median
42 days
Bayview is 11 days faster
Recent examples in Bayview
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-12779 | Improvement | Dama Construction | 2026-07-09 | 2026-08-12 | 34 | $150K |
| BP2026-11094 | Improvement | — | 2026-06-17 | 2026-07-14 | 27 | $95K |
| BP2026-08612 | Improvement | — | 2026-05-15 | 2026-06-04 | 20 | $8K |
| BP2026-04844 | Improvement | Ram Construction | 2026-03-27 | 2026-04-26 | 30 | $250K |
| BP2025-14593 | Improvement | — | 2025-07-28 | 2025-09-08 | 42 | $66K |