How long does a Demolition permit take in Banff Trail, Calgary?

Rolling 24 months · Sample: 52
Median days · Applied → Issued
6 days
Sample: 52 permits, last 24 months
Median days · Issued → Completed
29 days
From permit issuance to completion
City-wide median
4 days
Banff Trail is 2 days slower

Recent examples in Banff Trail

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-16699DemolitionCreative Solutions Contracting Services2026-09-012026-09-1110$0
BP2026-16700DemolitionCreative Solutions Contracting Services2026-09-012026-09-1110$0
BP2026-14681DemolitionWynn Development2026-08-042026-08-3127$0
BP2026-16069DemolitionWestern One Excavation2026-08-242026-08-262$0
BP2026-14978DemolitionGill S Express2026-08-072026-08-147$0