How long does a Commercial / Multi Family Project permit take in Arbour Lake, Calgary?

Rolling 24 months · Sample: 63
Median days · Applied → Issued
62 days
Sample: 63 permits, last 24 months
Median days · Issued → Completed
133 days
From permit issuance to completion
City-wide median
42 days
Arbour Lake is 20 days slower

Recent examples in Arbour Lake

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-15452ImprovementLeading Edge Developments2026-08-142026-09-0320$400K
BP2026-16144Unspecified2026-08-252026-08-261$9K
BP2026-09448Improvement2026-05-282026-08-0569$100K
BP2026-08891Improvement2026-05-212026-07-2161$80K
BP2026-10500ImprovementMountain View Sun Decks2026-06-092026-07-0728$175K