How long does a Commercial / Multi Family Project permit take in Arbour Lake, Calgary?
Median days · Applied → Issued
62 days
Sample: 63 permits, last 24 months
Median days · Issued → Completed
133 days
From permit issuance to completion
City-wide median
42 days
Arbour Lake is 20 days slower
Recent examples in Arbour Lake
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15452 | Improvement | Leading Edge Developments | 2026-08-14 | 2026-09-03 | 20 | $400K |
| BP2026-16144 | Unspecified | — | 2026-08-25 | 2026-08-26 | 1 | $9K |
| BP2026-09448 | Improvement | — | 2026-05-28 | 2026-08-05 | 69 | $100K |
| BP2026-08891 | Improvement | — | 2026-05-21 | 2026-07-21 | 61 | $80K |
| BP2026-10500 | Improvement | Mountain View Sun Decks | 2026-06-09 | 2026-07-07 | 28 | $175K |