How long does a Residential Improvement Project permit take in Applewood Park, Calgary?
Median days · Applied → Issued
22 days
Sample: 23 permits, last 24 months
Median days · Issued → Completed
61 days
From permit issuance to completion
City-wide median
17 days
Applewood Park is 5 days slower
Recent examples in Applewood Park
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-15071 | Improvement | — | 2026-08-10 | 2026-09-04 | 25 | $15K |
| BP2026-10385 | New | — | 2026-06-08 | 2026-08-06 | 59 | $96K |
| BP2026-08399 | New | — | 2026-05-14 | 2026-06-04 | 21 | $56K |
| BP2026-08001 | New | — | 2026-05-08 | 2026-05-14 | 6 | $56K |
| BP2026-07439 | Improvement | Royal Canadian Renovation | 2026-05-04 | 2026-05-09 | 5 | $0 |