How long does a Commercial / Multi Family Project permit take in Ambleridge, Calgary?
Median days · Applied → Issued
42 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
174 days
From permit issuance to completion
City-wide median
42 days
Same as Ambleridge
Recent examples in Ambleridge
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-11021 | New | Streetside Development | 2026-06-16 | 2026-07-24 | 38 | $963K |
| BP2026-11023 | New | Streetside Development | 2026-06-16 | 2026-07-24 | 38 | $1.2M |
| BP2026-10685 | New | — | 2026-06-11 | 2026-07-07 | 26 | $741K |
| BP2026-00305 | New | — | 2026-01-08 | 2026-02-23 | 46 | $706K |
| BP2025-21341 | New | — | 2025-10-31 | 2026-02-03 | 95 | $741K |