How long does a Commercial / Multi Family Project permit take in Ambleridge, Calgary?

Rolling 24 months · Sample: 6
Median days · Applied → Issued
42 days
Sample: 6 permits, last 24 months
Median days · Issued → Completed
174 days
From permit issuance to completion
City-wide median
42 days
Same as Ambleridge

Recent examples in Ambleridge

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-11021NewStreetside Development2026-06-162026-07-2438$963K
BP2026-11023NewStreetside Development2026-06-162026-07-2438$1.2M
BP2026-10685New2026-06-112026-07-0726$741K
BP2026-00305New2026-01-082026-02-2346$706K
BP2025-21341New2025-10-312026-02-0395$741K