How long does a Commercial / Multi Family Project permit take in Alyth Bonnybrook, Calgary?
Median days · Applied → Issued
63 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
86 days
From permit issuance to completion
City-wide median
42 days
Alyth Bonnybrook is 21 days slower
Recent examples in Alyth Bonnybrook
| Permit | Class | Contractor | Applied | Issued | Days to issue | Est. cost |
|---|---|---|---|---|---|---|
| BP2026-10852 | Improvement | — | 2026-06-14 | 2026-07-24 | 40 | $23K |
| BP2026-06964 | Improvement | — | 2026-04-28 | 2026-06-19 | 52 | $127K |
| BP2026-01637 | Improvement | — | 2026-02-03 | 2026-04-15 | 71 | $125K |
| BP2026-03372 | Improvement | Graham Infrastructure | 2026-03-05 | 2026-04-01 | 27 | $380K |
| BP2025-21790 | Unspecified | PCL Construction | 2025-11-10 | 2026-03-09 | 119 | $200K |