How long does a Commercial / Multi Family Project permit take in Alyth Bonnybrook, Calgary?

Rolling 24 months · Sample: 43
Median days · Applied → Issued
63 days
Sample: 43 permits, last 24 months
Median days · Issued → Completed
86 days
From permit issuance to completion
City-wide median
42 days
Alyth Bonnybrook is 21 days slower

Recent examples in Alyth Bonnybrook

PermitClassContractorAppliedIssuedDays to issueEst. cost
BP2026-10852Improvement2026-06-142026-07-2440$23K
BP2026-06964Improvement2026-04-282026-06-1952$127K
BP2026-01637Improvement2026-02-032026-04-1571$125K
BP2026-03372ImprovementGraham Infrastructure2026-03-052026-04-0127$380K
BP2025-21790UnspecifiedPCL Construction2025-11-102026-03-09119$200K